1z0-244 Oracle EBS R12: Advanced Supply Chain Planning

Loading demo links...

Showing 1–3 of 10 questions

Question 1

Which three recommended actions can be released from the Planners Workbench?

Select all that apply, then click Submit answer.

  • Planned Discrete Jobs

  • Planned Purchase Requisitions

  • Planned Purchase Orders

  • Sales Order Reschedule Recommendations

  • Sales Order demand

  • Forecast Consumption


Question 2

Which two actions offer a possible resolution to the exception message "Past due forecast"?

Select all that apply, then click Submit answer.

  • deleting the Forecast entry

  • revising the Forecast Due Date to a date later than the Plan Horizon Start Date

  • increasing Demand Priority of the Forecast entry

  • revising the Demand Priority Rules

  • revising the Forecast Due Date to a date later than the Demand Satisfied Date


Question 3

Identify five Material Constraints.

Select all that apply, then click Submit answer.

  • Effectivity Dates of Components In Bills of Material

  • Effectivity Dates of Operations in Routings

  • Resource efficiency and utilization

  • Order modifiers

  • Change of Shift timings

  • Tolerance fences

  • Substitute components

  • Effectivity Dates of Components in Engineering changes