Which one of the following is NOT a risk?
Select an option, then click Submit answer.
-
○
Customer might run into environmental issues with the municipality due to our product and missing ISO14000 certification.
-
○
Our subcontractor might charge us for the extra site visits as this particular case is not written down in our supply contract.
-
○
Logistic has informed the project team that the delivery which was expected last week has not arrived yet.
-
○
The acceptance criteria in the contract amendment might lead to additional effort as the wording could be misunderstood.