PDM_2002001060 CPM

Loading demo links...

Showing 4–6 of 15 questions

Question 4

Which one of the following is NOT a risk?

Select an option, then click Submit answer.

  • Customer might run into environmental issues with the municipality due to our product and missing ISO14000 certification.

  • Our subcontractor might charge us for the extra site visits as this particular case is not written down in our supply contract.

  • Logistic has informed the project team that the delivery which was expected last week has not arrived yet.

  • The acceptance criteria in the contract amendment might lead to additional effort as the wording could be misunderstood.

Question 5

Which document is developed along the risk management process, from identify risks through plan risk responses, to monitor and control risks?

Select an option, then click Submit answer.

  • List of risk triggers.

  • Risk register.

  • Risk mitigation plan.

  • Risk decision tree.

Question 6

Which inputs best support the resource demand plan update for a project?

Select an option, then click Submit answer.

  • Project organization chart, rollout schedule and project ID.

  • Project organization chart, required headcount, and required timeframe.

  • Rollout schedule, required headcount, project ID, required competences and required timeframe.

  • Material list, Rollout Schedule, WBS Code, and required timeframe.