Question 4 (Testing Software Quality Characteristics)

A company wants to develop a web site to implement an on-line sales channel. The company has decided to do some usability testing, but resources are limited. The usability testing has therefore to be done as efficient as possible. Which THREE techniques would you recommend?

[K4] 3 credits, 2 out of 3 correct 1 credit

Select all that apply, then click Submit answer.

  • SUMI

  • Usability laboratory

  • Use case testing

  • Heuristic evaluation

  • Equivalence partitioning

  • Pairwise testing

  • Exploratory testing

Question 5 (Test Process)

As a test analyst you are gathering data to support accurate metrics. Which of the following metrics would be MOST appropriate to use to monitor product quality?

[K2] 1 credit

Select all that apply, then click Submit answer.

  • Defects found versus defects expected

  • Tests run and tests passed

  • Test resources spent versus budget

  • Compliance to entry criteria

  • Product risks outstanding and new risks introduced

Question 6 (Test Process)

Which of the following criteria on test progress would enable the business to determine a likely ‘go live’ date?

(i) Number of tests planned versus number of tests executed

(ii) Number of high priority defects outstanding

(iii) The test team’s timesheets in order to show how much effort has been devoted to testing

(iv) Number of tests passed and number failed

(v) Number of defects found in each development area

(vi) The rate at which defects are being found

[K2] 1 credit

Select an option, then click Submit answer.

  • (ii), (iii), (iv)

  • (i), (iii), (v)

  • (i), (ii), (vi)

  • (iv), (v), (vi)