Question 7

What roles are authorized to create programs?

Select an option, then click Submit answer.

  • ○

    Only Program Leads and External Program Leads

  • ○

    Any role

  • ○

    Program designers only

  • ○

    Project leads only

Question 8

When viewing a Gantt Chart, the user can change the time grid settings to view it by....

Select an option, then click Submit answer.

  • ○

    Year, Month, Week, Day, Hour, Minute

  • ○

    Quarter, Month, Day, Hour, Minute

  • ○

    Year, Quarter, Month, Day

  • ○

    Year, Month, Week, Day, Minute

Question 9

In addition to tasks dependencies, how can you specify a delay between tasks?

Select an option, then click Submit answer.

  • ○

    with Slack Time in days or hours

  • ○

    with Start Delay time in days or hours

  • ○

    with Start-to-Start time in hours

  • ○

    None of these