Question 13 (Volume B)

Which statement applies to Stage Plans?

Select an option, then click Submit answer.

  • Always have the same duration as the Project Plan

  • Are produced at the same time as the Project Initiation Documentation

  • Assist the Project Manager in the day-to-day running and control of the project

  • Provide a baseline against which the Project Board monitor overall progress

Question 14 (Volume A)

Which risk response type is appropriate to respond to an opportunity?

Select an option, then click Submit answer.

  • Accept

  • Fallback

  • Exploit

  • Transfer

Question 15 (Volume B)

Which is a purpose of an End Stage Report?

Select an option, then click Submit answer.

  • Summarize progress to enable the Project Board to decide what action to take next

  • Summarize how the project performed against the version of the Project Initiation Documentation used to authorize it

  • Provide the detailed analysis of a deviation and offer options for the way to proceed

  • Provide a plan for the next stage of the project