Question 4 (Volume A)

Which is a responsibility of a risk owner?

Select an option, then click Submit answer.

  • Identify risks to the project that might occur in their department

  • Own and authorize the use of the risk budget to fund risk responses

  • Manage, monitor and control all aspects of an assigned risk

  • Determine project risk appetite

Question 5 (Volume B)

Which is a purpose of an Exception Plan?

Select an option, then click Submit answer.

  • Show the reason for the tolerance deviation from a Stage Plan or Project Plan

  • Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change

  • Identify the actions required to recover from the effect of a tolerance deviation

  • Define the changes which are within the scope of the change budget

Question 6 (Volume A)

Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?

Select an option, then click Submit answer.

  • Business Case

  • Plans

  • Progress

  • Quality