Question 7

The question below is based on the following chart of values relative to upper and lower control limits:

Which of the following types of variation is shown?

Select an option, then click Submit answer.

  • Special

  • Periodic

  • Common

  • Assignable

Question 8

Which of the following project characteristics would suggest using the PERT technique, rather than the critical path method?

Select an option, then click Submit answer.

  • Estimates of individual task times are probabilistic.

  • Project tasks are backward scheduled.

  • Due dates are needed to identify critical tasks.

  • Project management can determine the critical path.

Question 9

A company produces a part with a nominal diameter of 2.0 inches and a tolerance of ± 0.006 with a standard deviation of 0.001 inches. A sample has the average diameter of 1.996 inches with a standard deviation of 0.001 inches. What is the CPK and process capability?

Select an option, then click Submit answer.

  • 0.667, capable

  • 0.667, not capable

  • 0.333, capable

  • 0.333, not capable