Free CPIM-ECO – Execution and Control of Operations Practice Test Question

Free demo downloads

Loading demo links...

Showing 1–3 of 10 questions

Question 1

An immediate benefit of implementing lean manufacturing is improvement in:

Select an option, then click Submit answer.

  • ○

    employee development.

  • ○

    inventory valuation.

  • ○

    total quality.

  • ○

    lead time.

Question 2

The utilization of a downstream nonbottleneck resource is determined by:

Select an option, then click Submit answer.

  • ○

    a bottleneck resource.

  • ○

    theoretical capacity.

  • ○

    available capacity.

  • ○

    standard hours available.

Question 3

Optimizing a patient intake area for improved work flow is consistent with which 5S principle?

Select an option, then click Submit answer.

  • ○

    Sort

  • ○

    Set in order

  • ○

    Shine

  • ○

    Standardize