What does a cost baseline primarily represent?
Select an option, then click Submit answer.
- ○ Approved time-phased project budget
- ○ Contractor profit margin target
- ○ Unapproved preliminary cost estimate
- ○ Final actual cost total
Loading demo links...
Showing 1–12 of 12 questions
What does a cost baseline primarily represent?
Select an option, then click Submit answer.
Which estimate class is most detailed and accurate?
Select an option, then click Submit answer.
What is the primary purpose of contingency reserve?
Select an option, then click Submit answer.
How is estimate at completion best described?
Select an option, then click Submit answer.
Which method estimates costs using historical relationships?
Select an option, then click Submit answer.
What does net present value measure?
Select an option, then click Submit answer.
Which TWO items belong in a cost baseline? Select two.
Select all that apply, then click Submit answer.
Which TWO methods support bottom-up estimating? Select two.
Select all that apply, then click Submit answer.
Which TWO factors affect estimate accuracy? Select two.
Select all that apply, then click Submit answer.
DRAG DROP
Match each cost term to its correct description.
Items to match: Contingency reserve, Management reserve, Cost baseline, Actual cost.

Answer is in the explanation below.
DRAG DROP
Match each economic term to its correct meaning.
Items to match: Net present value, Internal rate of return, Payback period, Benefit-cost ratio.

Answer is in the explanation below.
CORRECT TEXT
The approved, time-phased budget used to measure cost performance is the cost ______.
Answer is in the explanation below.