Free CCE-CCC – Certified Cost Consultant / Cost Engineer (AACE International) Practice Test Question

Free demo downloads

Loading demo links...

Showing 10–10 of 10 questions

Question 10

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?

Select an option, then click Submit answer.

  • ○

    6,600

  • ○

    6,960

  • ○

    7,200

  • ○

    6,573