LSSYB Lean Six Sigma Yellow Belt

Loading demo links...

Showing 7–9 of 9 questions

Question 7

Which tool is best to utilize to assist in determining solution priorities?

Select an option, then click Submit answer.

  • Cost Benefit Analysis

  • Control Plan

  • FMEA

  • Response Plan

Question 8

If the production is for higher volume and monitoring and the Mean and variability is to be monitored for four machines producing product and the characteristic to be monitored is Variable Data, which SPC Chart is best to be selected?

Select an option, then click Submit answer.

  • Xbar-R Chart

  • Individual-MR Chart

  • NP Chart

  • CUSUM Chart

Question 9

80% of effects come from 20% of the possible causes. These 20% are called the:

Select an option, then click Submit answer.

  • Variations in the process

  • Vital Few

  • Cost to the process

  • Waste