Question 4

At which two stages will the Agile Release Train (ART) act as a one-team culture? (Choose two.)

Select all that apply, then click Submit answer.

  • Performing - Creating a flow of knowledge across the teams and the ART

  • Norming - Teams begin to form communities

  • Storming - Fostering continuous improvement

  • Collaborating - Pairing and sharing across the ART

  • Forming - The leaders will start to emerge

Question 5

What are the three key items communicated on the Program Board? (Choose three.)

Select all that apply, then click Submit answer.

  • Feature delivery dates

  • PI Objectives

  • Program risks

  • Milestones

  • Dependencies between teams

  • Team velocity

Question 6

When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?

Select an option, then click Submit answer.

  • That the feature can be completed by that team independently

  • That the team has not broken the feature into stories yet and has not identified dependencies

  • That it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains

  • That the team has been assigned, but the feature’ uépendencies have not been identified yet