E_S4HCON2022 SAP Certified Technology Specialist - SAP S/4HANA Conversion and SAP System Upgrade

Loading demo links...

Showing 7–9 of 10 questions

Question 7

You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.

The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.

Why are 40 Process Buckets executed in parallel?

Please choose the correct answer.

Response:

Select an option, then click Submit answer.

  • There is a maximum of 40 parallel R31oad processes within this specific downtime phase.

  • SUM is still running in uptime; the number of 40 defined R31oad processes is considered.

  • The number of CPU cores does not allow more than 40 R31oad processes to be run in parallel.

  • These are 40 pairs of R3load processes, so there are 80 R3load processes running.

Question 8

You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What do you need to consider? Please choose the correct answer.

Select an option, then click Submit answer.

  • The upgrade of the PRD must be finished before you start new development in the DEV.

  • The transport domain of systems DEV and QAS must differ from the transport domain of system PRD.

  • The transport between Unicode and non-Unicode systems is forbidden.

  • The upgrade of the PRD must be finished before you import any transports from the upgraded DEV system into the PRD.

Question 9

What can you achieve by setting the SUM parameter "migration_only" to 1 in parameter file SAPup_add.par?

Please choose the correct answer.

Response:

Select an option, then click Submit answer.

  • An upgrade of the software components is performed, without changing the database type.

  • A change of the database type is performed, without changing the software components.

  • An SAP S/4HANA conversion is performed, without adapting the customer data.

  • A migration of the SAP system to a new hardware is performed, without performing an SAP S/4HANA conversion.