Question 1

You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration?

There are 3 correct answers to this question. Response:

Select all that apply, then click Submit answer.

  • Generation of the new ABAP loads in phase RUN_SGEN_GENER8

  • Import of upgrade and language data from the download directory in phase TABIM UPG

  • Activation of dictionary objects in phase ACT_UPG

  • Creation of application tables in the SAP HANA database in phase EU_CLONE_MIG_DT_CREATE

  • Import of dictionary objects from the download directory in phase DDIC_UPG


Question 2

What are the benefits of using the Benchmarking option of the DMO for SUM?

There are 2 correct answers to this question. Response:

Select all that apply, then click Submit answer.

  • You can obtain migration duration files that can be used to optimize the next runs from a previous benchmark run.

  • You can find the optimal number of parallel R31oad processes by monitoring host performance.

  • You can verify that the content of the download directory matches the stack.XML file.

  • You can record the modification adjustment during migration and use the transports in the next runs.


Question 3

In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?

There are 2 correct answers to this question. Response:

Select all that apply, then click Submit answer.

  • Upgrading to SAP ECC 6.08 without using DMO

  • Using DMO when applying Support Packages to SAP ECC 6.07

  • SAP S/4HANA conversion to SAP S/4HANA 1709

  • Updating to SAP ECC 6.07 using DMO