You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration?
There are 3 correct answers to this question. Response:
Select all that apply, then click Submit answer.
-
○
Generation of the new ABAP loads in phase RUN_SGEN_GENER8
-
○
Import of upgrade and language data from the download directory in phase TABIM UPG
-
○
Activation of dictionary objects in phase ACT_UPG
-
○
Creation of application tables in the SAP HANA database in phase EU_CLONE_MIG_DT_CREATE
-
○
Import of dictionary objects from the download directory in phase DDIC_UPG