C_TS450_2020 SAP Certified Application Associate - SAP S/4HANA Sourcing and Procurement - Upskilling for ERP Experts

Loading demo links...

Showing 1–3 of 10 questions

Question 1

Where can you specify whether consumption-based planning or requirements-based planning will be performed? Note: There are 2 correct Answers to this question.

Select all that apply, then click Submit answer.

  • In the plant data of a material

  • On the initial screen of the planning run

  • In the customizing of the plant parameters

  • In the MRP area data of a material

Question 2

What are objectives of using safety stock for a material? Note: There are 2 correct Answers to this question.

Select all that apply, then click Submit answer.

  • To cover unexpected requirements during the safety time

  • To cover normal requirements in case of delivery delays.

  • To cover expected average requirements during the replenishment lead time

  • To cover unexpected consumption during the replenishment lead time

Question 3

In which processes can a bill of material (BOM) be used to determine the components of a finished product? Note: There are 3 correct answer

Select all that apply, then click Submit answer.

  • Third-party order processing

  • Product costing

  • Supplier consignment

  • Material requirements planning

  • Subcontracting