Question 1

Resources

Which of the following transactions can you use to post actual cost for external processing.

Note : there are 2 correct answer for this question.

Select all that apply, then click Submit answer.

  • Approval of a service entry sheet

  • Posting a goods receipt

  • Creating a service entry sheet

  • Approval of a good receipt.

  • Creating a purchase order.

Question 2

Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

Select all that apply, then click Submit answer.

  • Project-relevant purchase orders

  • Capacity requirements

  • Maintenance orders assigned to an activity

  • Production orders assigned to WBS elements

Question 3

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

Select all that apply, then click Submit answer.

  • You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"

  • You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"

  • You can always maintain the actual start and finish date of a WBS element

  • You can only maintain the actual start of a WBS element if the finish date is not maintained