Question 1

Which of the following are consequence of releasing a phase?

NOTE: There are 2 correct answers to this question

Select all that apply, then click Submit answer.

  • Predecessor phases are assigned the status locked

  • Lower-level tasks and checklist are release

  • Additional tasks cannot be added to the phase

  • The phase type is set to read-only

Question 2

You are in portfolio management and create a project system (PS) project from an item.

Which parts you add afterwards directly in PS?

NOTE: There are 3 correct answers to this question

Select all that apply, then click Submit answer.

  • Network activities

  • PS texts

  • Documents

  • Network components

  • WBS elements

Question 3

Which of the following multi-currency scenario are supported?

NOTE: There are 2 correct answers to this question

Select all that apply, then click Submit answer.

  • Multiple planning currencies can be used in one bucket

  • Item currency can be inherited from the assigned bucket

  • Bucket in a portfolio can use different currencies

  • Items In a bucket an only use bucket currencies