C_IBP_2302 SAP Certified Application AssociateSAP IBP for Supply Chain (2302)

Loading demo links...

Showing 1–3 of 10 questions

Question 1

You are setting up planing with lot sizes.What are some of the properties of lot sizes that you need to be aware of?Note: There are 2 correct answers to this question.

Select all that apply, then click Submit answer.

  • Lot sizes are applicable for production and handling quantities.

  • Periodic lot size setting overrides the minimum lot size.

  • Lot sizes are time-independent master data settings.

  • Lot sizes are applicable for production and transportation quantities.

Question 2

What do you need to be aware of when using multiple pairs of key figures in one copy operator? Note: There are 2 correct answers to this question.

Select all that apply, then click Submit answer.

  • Copying multiple key figures can be processed sequentially.

  • If necessary source key figures values are disaggregated.

  • Copying multiple key figures on different planning levels is not possible.

  • If necessary target key figures values are disaggregated.

Question 3

What are the outputs of the Calculate Target Inventory Components Operator?Note: There are 3 correct answers to this question.

Select all that apply, then click Submit answer.

  • Target Cycle Stock

  • Recommended Safety Stock

  • Component Usage

  • Reorder Point

  • Target Pipeline Stock