Question 4

What is the purpose of the Solution Validation activity in the Explore Phase? (Choose three.)

Select all that apply, then click Submit answer.

  • Log additional scope items

  • Verify technical installation

  • Challenge changes to standard

  • Identify gaps

  • Educate project participants

Question 5

Which new project roles are introduced with the SAP Activate Methodology for the Agile delivery approach, compared to Waterfall? (Choose two.)

Select all that apply, then click Submit answer.

  • Integration Lead

  • Scrum Master

  • Design Thinking Coach

  • Product Owner

Question 6

What does a Cutover involve?

Select an option, then click Submit answer.

  • Presenting completed User Story to Key Users

  • Closing Quality Gate

  • Switching productive business operations from one system to another

  • Transporting new Product Increment in the Development System