Question 10

After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials).

Which of the following planning file entries for this material are set by the system?

Select an option, then click Submit answer.

  • The BOM explosion and the NETPL planning indicator

  • The BOM explosion indicator

  • The BOM explosion, the NETCH, and the NETPL planning indicators

  • The NETCH and NETPL planning indicators