Free C_TSCM42_66 – SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 Practice Test Question

Free demo downloads

Loading demo links...

Showing 4–6 of 10 questions

Question 4

What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)

Select all that apply, then click Submit answer.

  • ○

    The order is no longer relevant for material requirements planning.

  • ○

    Capacity requirements are set to null.

  • ○

    Confirmations are no longer possible.

  • ○

    Reservations are no longer relevant for material requirements planning.

  • ○

    The order and its operations receive the system status Locked (LKD).

Question 5

What do you have to consider when you use SAP ECC long-term planning (LTP)? (Choose two)

Select all that apply, then click Submit answer.

  • ○

    A planning scenario must be released before it can be used in LTP.

  • ○

    Reorder point planned materials can be included in LTP.

  • ○

    LTP focuses on the operational planning of important components.

  • ○

    LTP creates purchase requisitions for external procurement.

Question 6

What is a feature of the simu-lation mode for material requirements planning in SAP ECC?

Select an option, then click Submit answer.

  • ○

    It calculates the delay time which may occur in planning.

  • ○

    It triggers multilevel bottom-up scheduling.

  • ○

    It propagates exception messages from a component to the finished product.

  • ○

    It posts planning results to the database automatically.