Question 4

You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: There are 2 correct answers to this question.

Select all that apply, then click Submit answer.

  • Checking control must have an overall profile assigned in customizing.

  • Indicator Relevant for finite scheduling must be set.

  • Checking rule and group must be assigned.

  • PRT Availability check must be set.


Question 5

Which reports can you access via the order and resource reporting transaction in advanced planning? There are 3 correct answers to this question

Select all that apply, then click Submit answer.

  • Production list

  • WIP list

  • Production overview

  • Operation list

  • Planning file entries


Question 6

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP"/OS)?

Select an option, then click Submit answer.

  • Use a propagation range.

  • Use a planning group.

  • Use a resource group.

  • Use a heuristic.