Question 4

During PI Planning, which two tasks are part of the Scrum Master's role in the first team breakout? (Choose two.)

Select all that apply, then click Submit answer.

  • ○

    Identify as many risks and dependencies as possible for the Management Review

  • ○

    Facilitate the coordination with other teams for dependencies

  • ○

    Be involved in the Program Backlog refinement and preparation

  • ○

    Provide clarifications necessary to assist the team with their story estimating and sequencing

  • ○

    Review and reprioritize the Team Backlog as part of the preparatory work for the second team breakout

Question 5

Which of the following are the purposes of the IP Iteration? (Choose Four)

Select all that apply, then click Submit answer.

  • ○

    enable continuous learning

  • ○

    Allow time for innovation

  • ○

    advance development infrastructure

  • ○

    serve as estimation buffer

Question 6

What is an anti-pattern for the IP Iteration? (Choose two.)

Select all that apply, then click Submit answer.

  • ○

    To plan work for the IP Iteration during PI Planning

  • ○

    To ensure all stories and teams' PI plans are completed prior to the IP Iteration

  • ○

    To allow for sufficient capacity in the program roadmap

  • ○

    To wait for the IP Iteration to fix defects

  • ○

    To minimize lost capacity when people are on vacation or holidays