Question 7 (Volume B)

During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

Select an option, then click Submit answer.

  • ○

    Project Product Description

  • ○

    Business Case

  • ○

    Project Brief

  • ○

    Project mandate

Question 8 (Volume A)

What is the definition of a project outcome?

Select an option, then click Submit answer.

  • ○

    A measurable improvement that is perceived as an advantage by one or more stakeholders

  • ○

    The reason for the project

  • ○

    The result of the change derived from using the project's outputs

  • ○

    The project's specialist products.

Question 9 (Volume C)

Which is a purpose of the Directing a Project process?

Select an option, then click Submit answer.

  • ○

    Create and authorize the project mandate

  • ○

    Ensure that work on products allocated to the team is authorized and agreed

  • ○

    Control the day-to-day running of the project

  • ○