Showing 4–6 of 11 questions

Question 4 (Volume B)

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

Select an option, then click Submit answer.

  • controls

  • products

  • project management team

  • stages

Question 5 (Volume B)

Which is a purpose of the Managing a Stage Boundary process?

Select an option, then click Submit answer.

  • Provide the Project Board with sufficient information for approving the next stage

  • Approve the next Stage Plan

  • Review and close any risks and issues identified during the previous stage

  • Control the link between the Project Manager and the Team Manager(s)

Question 6 (Volume B)

Which is a minimum requirement for applying the ‘quality’ theme?

Select an option, then click Submit answer.

  • Completed products must be reviewed using the PRINCE2 quality review technique

  • Independent reviews of the project must be carried out throughout its lifecycle

  • Approval records must be kept to show formal approval has been given

  • Quality criteria for products must be specified in their product descriptions