Question 1

Which statement explains the setting of the cost tolerance for a project in an agile context?

Select an option, then click Submit answer.

  • Cost tolerance is flexed

  • Cost tolerance can be fixed or flexed

  • Cost tolerance can be fixed and flexed

  • Cost tolerance is fixed


Question 2

Which statement about the PRINCE2 Agile behaviour ‘collaboration’ is CORRECT?

Select an option, then click Submit answer.

  • It allows many small learnings to accumulate over time

  • It allows the delivery team to decide how best to get the job done

  • It creates a shared ownership of goals

  • It uses the most effective channel to communicate


Question 3

What is an epic?

Select an option, then click Submit answer.

  • A low-level requirement

  • A fine-grained user story

  • A detailed feature

  • A high-level requirement