Question 4

Who is responsible for the “definition of done”?

Select an option, then click Submit answer.

  • The team

  • The Product Owner

  • Management

  • Project manager

Question 5

The process of reviewing, testing, and accepting implemented features is called:

Select an option, then click Submit answer.

  • Retrospective.

  • Stakeholder review.

  • Scope verification.

  • Iteration planning.

Question 6

How is the participatory design process characterized?

Select an option, then click Submit answer.

  • A well-planned and well-documented process is documented for each of the iterations in the project.

  • Users including project team members participate in the planning process for the project plan.

  • End users participate and assist in the design process from the beginning of the project.

  • A high level brainstorming process is conducted for the project team and the project sponsor.