Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Select an option, then click Submit answer.
-
○
Bottom-up
-
○
Parametric
-
○
Analogous
-
○
Three-point