Question 10 (Exam Set D)

The independence of two events in which the occurrence of one is not related to the occurrence of the other is called _______.

Select an option, then click Submit answer.

  • Event phenomenon
    Lead

  • Independent probability
    client

  • Statistical independence
    Project manager

  • Statistical probability



    Change control board




Question 11 (Exam Set B)

A graphic display of resource usage hours is called a/an_________________.

Select an option, then click Submit answer.

  • Organizational chart

  • Responsibility matrix

  • WBS

  • Histogram


Question 12 (Exam Set D)

You are the project manager of a project. The project plan has been developed. A project end date has been established. The customer later requesters additional work to be included in the project, but will not renegotiate the end date. Cost is not a factor. What should the project team do immediately?

Select an option, then click Submit answer.

  • Invoke the change control process

  • Initiate contingency plans

  • Modify the original project scope to include the additional work

  • Commit to original project scope and open a new project to handle additional work