Question 13 (New Update)

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Select an option, then click Submit answer.

  • ○

    Informal communication

  • ○

    Internal communication

  • ○

    Formal communication

  • ○

    Horizontal communication