Question 13 (Volume A)

Which of the following is a tool or technique of the Collect Requirements process?

Select an option, then click Submit answer.

  • Group decision making techniques

  • Project management information system

  • Alternative identification

  • Communication requirement analysis


Question 14 (Volume A)

Which process group can be performed outside the project's scope of control?

Select an option, then click Submit answer.

  • Planning

  • Monitoring and Control

  • Closing

  • Initiating


Question 15 (Volume A)

Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

Select an option, then click Submit answer.

  • Risk response planning

  • Risk monitoring and control

  • Performance reporting