1z0-1075-22 Oracle Manufacturing Cloud 2022 Implementation Professional

Loading demo links...

Showing 4–6 of 10 questions

Question 4

Identify the three changes that are allowed to be made to active Work Definition in a Work Center, without creating a new version.

Select all that apply, then click Submit answer.

  • Delete an Operation

  • Costing Priority

  • Production Priority

  • Add an Operation

  • Completion Subinventory

Question 5

Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.

Select all that apply, then click Submit answer.

  • Set the nonstocked item to be back-to-back enabled in Product Information Management (PIM).

  • Set the global sourcing rule in GOP to determine supply creation option as Make.

  • Set a local sourcing rule in GOP to determine supply creation option as Make.

  • Create Supply Order Orchestration Defaulting and Enrichment Rule for the nonstocked item.

  • Create Supply Chain Orchestration Supply Execution Document Creation Rule for the nonstocked item.

Question 6

While creating an item in Product Information Management (PIM), the following two item templates are selected in sequence and applied.

1. Template: Finished Goods (WIP = No, Customer Ordered = Yes)

2. Template: Sub-assembly (WIP = Yes, Customer Ordered = No)

Identify the Item Attribute values in the application.

Select an option, then click Submit answer.

  • WIP = Yes, Customer Ordered = Yes

  • WIP = Yes, Customer Ordered = No

  • WIP = No, Customer Ordered = Yes

  • WIP = No, Customer Ordered = No