1z0-1062-21 Oracle Incentive Compensation Cloud 2021 Implementation Essentials

Loading demo links...

Showing 1–3 of 10 questions

Question 1

The 'Run Crediting and Rollup’process request completes successfully but no credits are created. Which three configurations must be verified?

Select all that apply, then click Submit answer.

  • Participants assigned to a direct credit rule do not have the Manager role.

  • The same participants are not assigned to multiple credit rules in the hierarchy.

  • The transaction event date falls between thecredit rule start and end dates.

  • The 'Deploy Credit Rule' process was run after the credit rules were created.

  • 'EnableDirect Crediting* is set to 'Yes' on the 'Manage Parameters'page.

  • The 'Deploy Compensation Plans' process was run after thecredit rules were created.


Question 2

Which three are reports you can customize few Mobile Commissions?

Select all that apply, then click Submit answer.

  • Payments: Payment transactions and related details of the sales participant

  • Credits: Credits and related details of the sales participant

  • Analytics: Details of the recent analysis of the sales participant

  • Disputes: Details of the recent disputes raised by the sales participant

  • Reimbursements:Reimbursements and related details of the sale*, ii.ntic ip.int


Question 3

Which three statements are true regarding Classification?

Select all that apply, then click Submit answer.

  • Classification splits the credits among the participant credit receivers.

  • Classification rules are used to classify transactions into meaningful credit categories.

  • Rule criteria involve one or more transaction attributes.

  • Qualifiers are ANDed and qualifier attribute values are ORed.

  • Classification process must be run before the Crediting process.