1z0-1057 Oracle Project Portfolio Management Cloud 2019 Implementation Essentials

Loading demo links...

Showing 7–9 of 10 questions

Question 7

Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

Select an option, then click Submit answer.

  • Effort

  • Cost

  • Manual Entry

  • Remaining Plan


Question 8

When implementing Project Performance Reporting, your customer has the following requirements:

Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.

As long as a project cost is less than the threshold, the project should be shown as on-track.

Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)

Select an option, then click Submit answer.

  • multiple threshold levels

  • single threshold level value

  • single threshold level range

  • multiple threshold level value


Question 9

As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter. Identify the reason for this problem. (Choose the best answer.)

Select an option, then click Submit answer.

  • Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.

  • Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.

  • You can enable automatic reprocessing of expenditure items processed before the burden schedule change.

  • All expenditure items charged to the task use the new burden schedule.