Question 7

Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.

Identify the correct statement about the RBS and new resources. (Choose the best answer.)

Select an option, then click Submit answer.

  • If the “Allow resource changes at project level” option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.

  • If the “Allow resource changes at project level” option is set to No for the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.

  • If the “Allow resource changes at project level” option is set to Yes for the RBS, the new resources are available automatically at project level.

  • If the “Allow resource changes at project level” option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.


Question 8

You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)

Select an option, then click Submit answer.

  • On Hold > Pending Acceptance > Active

  • On Hold > Pending Approval > Active

  • Pending Approval > Pending Acceptance > Active

  • Pending Acceptance > Pending Approval > Active


Question 9

You have defined two expenditure types, but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)

Select an option, then click Submit answer.

  • The two expenditure types are not assigned to the reference data set that is assigned to the project unit
    in which the transaction is performed.

  • The two expenditure types are not assigned to the reference data set that is assigned to the project-owning organization in which the transaction is performed.

  • The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.

  • The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.