Question 4

A customer has a primary datacenter with 12 Nutanix blocks distributed across three racks. The customer wants to achieve the most resiliency possible. They also have a datacenter in a branch office that is 400 kilometers away from the primary datacenter.

Which two solutions should be used? (Choose two.)

Select all that apply, then click Submit answer.

  • Time Stream to a remote site

  • Async DR to a remote site

  • Rack awareness

  • Block awareness


Question 5

Refer to the exhibit.

An administrator has an existing cluster and needs to improve performance using AHV

Turbo. Which two items are required to achieve even greater performance? (Choose two.)

Select all that apply, then click Submit answer.

  • Workloads are multi-threaded.

  • VMs have one vCPU configured.

  • VMs have multi-queue disabled.

  • VMs have more than one vCPU.


Question 6

An administrator has a custom backup application that requires a 2TB disk and runs in

Windows. Throughput is considerably lower than expected.

The application was installed on a VM with the following configuration:

• Four vCPUs with one core/vCPU

• 4GB of Memory

• One 50GB vDisk for the Windows installation

• One 2TB vDisk for the application

What is the recommended configuration change to improve throughput?

Select an option, then click Submit answer.

  • Increase the number of cores per vCPU

  • Increase the vCPUs assigned to the VM

  • Span the 2TB disk across four vDisks

  • Add 4GB of memory to the VM