Question 4

Which of the following are typical milestones from TI scope of work?

Select an option, then click Submit answer.

  • IS13.1 Main Equipment on Site, MS14 Delivery Acceptance, MS15 Implementation starts and MS16 Implementation Ends.

  • MS15 Implementation starts and MS16 Implementation Ends.

  • MS11 Construction Works starts and MS17 Site Acceptance.

  • MS12 Construction Works ends and MS13 Ready for Implementation.

Question 5

What are the defined Gates in the NSN Sales Work Flow?

Select an option, then click Submit answer.

  • 1. Customer Selection
    2. Go/No Go
    3. Bid/No Bid
    4. Approval/No Approval
    5. Deal/No Deal
    6. Start Delivery

  • 1. Receive the RFQ
    2. Define Bid Team
    3. Create Customer Offer
    4. Negotiate Contract
    5. Prepare Project Plan

  • 1. Identify Customer Needs
    2. Develop a Solution
    3. Prepare Commercial Offer
    4. Negotiate Contract
    5. Prepare PTA

  • 1. Receive RFQ
    2. Develop Solution
    3. Prepare Commercial Offer
    4. Negotiate Contract
    5. Prepare for Delivery

Question 6

An accuracy KPI has dropped significantly compared to previous periods. After some initial checks it turns out that the data is correct. What is the right way to proceed?

Select an option, then click Submit answer.

  • Organize a meeting with NPO in order to make a action plan to improve.

  • Communicate the deviation to the project stakeholders

  • Organize a meeting with key team members in order to identify root causes and make an action plan to improve.

  • Inform the CT head on the next CT meeting.