Question 7

Which of the following inputs are part of the Sales to Delivery handover?

Select an option, then click Submit answer.

  • ○

    As sold cost estimate, project plan and PTA.

  • ○

    Customer PO, draft of the contract and schedule.

  • ○

    Cost assumptions, cost county database updated and risk log.

  • ○

    PTA, RFQ and approved cost baseline.

Question 8

Which are the 3 key players in the Sales Phase according to the TRICORN model?

Select an option, then click Submit answer.

  • ○

    Company owner, solution architect and project manager.

  • ○

    Case owner, customer solution owner and delivery project owner.

  • ○

    Case owner, company owner and solution architect.

  • ○

    Care manager, project manager and logistics manager.

Question 9

If the project has accepted the supplier work and updated the progress tracking tool, what is the next step for a project which is not using RTI 4.0 (Real Time Interface version 4)?

Select an option, then click Submit answer.

  • ○

    Cost & Progress manager (EVM) updates SAP with the Billing Block release date.

  • ○

    Cost & Progress manager (EVM) updates SAP with the Goods Receipt date.

  • ○

    Logistics coordinator updates SAP with the Billing Block release date.

  • ○

    Logistics coordinator updates SAP with the Goods Receipt date.