Showing 4–6 of 10 questions

Question 4

Under which heading in the POTI model should the current performance level of an operational area be recorded?

Select an option, then click Submit answer.

  • Process

  • Organization

  • Technology

  • Information

Question 5

In a multiple programme environment, which role may be performed by a ‘corporate portfolio board’?

Select an option, then click Submit answer.

  • Sponsoring group

  • Programme board

  • Design authority

  • Programme office

Question 6

What type of programme may also be referred to as a ‘must do’ programme?

Select an option, then click Submit answer.

  • Portfolio

  • Emergent

  • Vision-led

  • Compliance