Which of the following is an example of the test closure activity indicated as "lessons learned"?
Select an option, then click Submit answer.
-
○
Archive all the test results of the acceptance testing phase.
-
○
Deliver a list of the open defects of a software product released into production to the service desk team.
-
○
Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects.
-
○
Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing.