TM12 ISTQB-BCS Certified Tester Advanced Level- Test Manager (2012)

Loading demo links...

Showing 7–9 of 9 questions

Question 7

Which of the following is an example of the test closure activity indicated as "lessons learned"?

Select an option, then click Submit answer.

  • Archive all the test results of the acceptance testing phase.

  • Deliver a list of the open defects of a software product released into production to the service desk team.

  • Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects.

  • Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing.

Question 8

Which of the following statements about management of product quality risks in mature organizations with respect to the lifecycle, is true?

Select an option, then click Submit answer.

  • Mature organizations address product quality risks associated to non-functional characteristics only during the system test phase.

  • Mature organizations are aware that the contribution of testing to analysis of product quality risks is very important. The analysis should occur throughout the entire life cycle.

  • Mature organizations don’t waste time identifying the sources of risks. They only focus on identifying product quality risks.

  • Mature organizations are aware that risk management of product quality risks only occurs during testing.

Question 9

The following chart plots the cumulative number of defects opened against the cumulative number of defects closed during system testing of a software product.

Which of the following statements is true?

Select an option, then click Submit answer.

  • The chart indicates that you have plenty of problems left to find.

  • The chart can be used to reveal test progress problems.

  • The chart seems to indicate that the defect management process is not working well.

  • The chart seems to indicate that the defect management process is working well.