Question 1 (Exam Pool A)

Out of the following, what is not needed to specify in defect report?

Select an option, then click Submit answer.

  • How to fix the defect

  • Severity and priority

  • Test environment details

  • How to reproduce the defect


Question 2 (Exam Pool B)

Which type of review has the following main purposes:

discussing, making decisions, evaluating alternatives, finding defects, solving technical problems and checking conformance to specifications, plans, regulations, and standards?

Select an option, then click Submit answer.

  • Technical Review

  • Inspection

  • Walkthrough

  • Informal review


Question 3 (Exam Pool C)

A Test Manager conducts risk assessment for a project One of the identified risks is: ''The sub-contractor may fail to meet his commitment" If this risk materializes, it will lead to delay in completion of testing required for the current cycle.

Which of the following sentences correctly describes the risk?

Select an option, then click Submit answer.

  • It is a project risk since successful completion of the project depends on successful and timely completion of the tests

  • It is a product risk since any risk associated with development timelines is a product risk

  • It is a product risk since default on part of the sub-contractor may lead to delay in release of the product

  • It is no longer a risk for the Test Manager since an independent party (the sub-contractor) is now managing it