Question 4 (Defect Management)

You are the Test Manager of a project that adopts a V-model with four formal levels of testinG. unit, integration, system and acceptance testing.

On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing.

Assume that no requirements defects have been reported after the release of the product.

Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness?

K3 2 credits

Select all that apply, then click Submit answer.

  • Number of defects found during the requirements review

  • Total number of defects attributable to requirements found during unit, integration, system and acceptance testing

  • Total number of defects found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing

  • Time to conduct the requirements review

  • Total number of defects attributable to requirements, found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing

Question 5 (Reviews)

Which of the following factors could negatively influence a review?

K2 1 credit

Select an option, then click Submit answer.

  • Include people with the adequate level of knowledge, both technical and procedural

  • Include people who are detail-oriented and scrupulous at finding issues

  • Include as many people as possible in order to have more viewpoints about possible problems on the item under review

  • Include people able to contribute to a clear, thoughtful, constructive and objective discussion

Question 6 (Test Management)

Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?

K2 1 credit

Select an option, then click Submit answer.

  • Test reporting activities can’t be influenced by the use of an iterative lifecycle model with short iterations

  • Test reporting activities are not important for projects adopting an iterative lifecycle model with short iterations

  • Test reporting activities are less important for projects adopting an iterative life cycle model with short iterations. They should be performed at the end of the last iteration

  • Test reporting activities are still important with an iterative lifecycle. The reports can be used to conduct post-iteration review sessions before starting with the next iteration