Question 10
(Exam Pool B)
Which of the following metrics could be used to monitor progress along with test preparation and execution? [K1]
Select an option, then click Submit answer.
-
○
The total number of tests planned
-
○
The total number of requirements to be tested
-
○
The failure rate in testing already completed
-
○
The number of testers used for test execution so far