Question 4 (Scenario 9 "Test Management Documentation")

Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)

Select all that apply, then click Submit answer.

  • ○

    Identify test staff members that will be involved in the system test

  • ○

    Define test career paths

  • ○

    Understand the software development life cycle used by the software house

  • ○

    Assess the testing that needs to be done to minimize the risks

  • ○

    Issue the test strategy document for review

  • ○

    Define a master test plan template

  • ○

    Perform a project risk analysis

Question 5 (Scenario 4, V2 "Test Management Tool")

Which of the following would be the TWO most appropriate examples of entry criteria documented in the system integration test plan? 2 credits

Select all that apply, then click Submit answer.

  • ○

    The percentage of decision coverage achieved during unit testing.

  • ○

    The availability of the latest version of the capture-replay tool (for testing the interface with the newly developed test management tool).

  • ○

    The sign-off of a performance test software release note (test item transmittal report) by both development and testing showing that system performance meets the specified acceptance criteria.

  • ○

    The percentage of acceptance test procedures scheduled for execution.

  • ○

    The percentage of requirements coverage achieved during system integration test.

Question 6 (Scenario 7 "Test Estimation")

Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)

Select all that apply, then click Submit answer.

  • ○

    Test planning, test case preparation and test execution for each of the four iterations

  • ○

    Work should be explicitly allocated to test completion, test management, installation and to training on using the system

  • ○

    Activities to deploy the system in the user environment

  • ○

    Regression testing in the second, third and fourth iterations

  • ○

    Development activities for unit and integration testing

  • ○

    Reviews on requirements documentation

  • ○

    Defining test environment requirements for system testing