Which of the following NIST documents provides a guideline for identifying an information system as a National Security System?

Select an option, then click Submit answer.

  • NIST SP 800-37

  • NIST SP 800-59

  • NIST SP 800-53

  • NIST SP 800-60

  • NIST SP 800-53A

Question 11

You are the project manager for GHY Project and are working to create a risk response for a negative risk. You and the project team have identified the risk that the project may not complete on time, as required by the management, due to the creation of the user guide for the software you're creating. You have elected to hire an external writer in order to satisfy the requirements and to alleviate the risk event. What type of risk response have you elected to use in this instance?

Select an option, then click Submit answer.

  • Transference

  • Exploiting

  • Avoidance

  • Sharing

Question 12

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Select an option, then click Submit answer.

  • Project Management Information System

  • Integrated Change Control

  • Configuration Management System