Question 13

Your project has several risks that may cause serious financial impact should they happen. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They'd like for you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?

Select an option, then click Submit answer.

  • Quantitative analysis

  • Contingency reserve

  • Risk response

  • Risk response plan

Question 14

You are advising a school district on disaster recovery plans. In case a disaster affects the main IT centers for the district they will need to be able to work from an alternate location. However, budget is an issue. Which of the following is most appropriate for this client?

Select an option, then click Submit answer.

  • Cold site

  • Off site

  • Hot site

  • Warm site

Question 15

You work as the project manager for Bluewell Inc. You are working on NGQQ Project for your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

Select an option, then click Submit answer.

  • Risk mitigation

  • Risk acceptance

  • Risk avoidance

  • Risk transference