C2010-825 Rational Team Concert V6

Loading demo links...

Showing 4–6 of 8 questions

Question 4

An administrator is comparing the capabilities provided by the Jazz Team Server to those delivered by individual Jazz applications.

What is an example of the Jazz Team Server capabilities?

Select an option, then click Submit answer.

  • An agile development environment.

  • Shared services to all Jazz applications.

  • Process engineering for all Jazz applications.

  • Advanced source control for geographically distributed teams.

Question 5

An administrator would like to prevent source code check-ins without a review and has added the Code Review Summary to the work item editor presentation.

What additional step must be taken?

Select an option, then click Submit answer.

  • create Prevent Check-ins rule

  • create Approval Template

  • add appropriate preconditions

  • add Approval state to workflow

Question 6

A report author needs to produce a JRS report that only shows high priority work items.

How can this be accomplished?

Select an option, then click Submit answer.

  • Set up traceability links.

  • Link the report to a query.

  • Limit the project scope of the report

  • Add an attribute condition to the report.