Question 1 (Exam Pool B)

Regarding the overload capacity of UPS5000-E, which of the following statements is correct ( )

Select all that apply, then click Submit answer.

  • Inverter 110% overload for 60 minutes

  • Inverter 110% overload for 120 minutes

  • Bypass 135% overload for 120 minutes

  • Bypass 135% overload long-term operation

Question 2 (Exam Pool B)

FusionModule1000A V2R3 version 40-foot IT scene can provide the number of cabinets (multiple choice)

Select all that apply, then click Submit answer.

  • 5

  • 6

  • 7

  • 8

  • 9

Question 3 (Exam Pool B)

What certifications do Huawei precision column cabinets have (multiple choice)

Select all that apply, then click Submit answer.

  • Earthquake resistance

  • CE

  • UL

  • Thiel