Question 4

Draining impurities from the refrigerant pipe should

Select all that apply, then click Submit answer.

  • ○

    Block one of the pipe ports.

  • ○

    Fill the pipe with high-pressure nitrogen.

  • ○

    Quickly remove the pipe plug and avoid facing people to prevent injury.

  • ○

    To discharge nitrogen from the outdoor unit


Question 5

After the UPS5000-E system is installed, which of the following items need to be checked?

Select all that apply, then click Submit answer.

  • ○

    if UPS and battery system mechanical installation is firm and stable

  • ○

    if the cable layout considers other system wiring in the future

  • ○

    if the ground connection is reliable

  • ○

    The positive and negative terminals of the battery are wired correctly.


Question 6

On the NetEco, the door status is always open, we can identify with the faulty by ( ).

Select all that apply, then click Submit answer.

  • ○

    Checking whether the door is closed.

  • ○

    Checking whether cable are connected to the access actuator.

  • ○

    Checking whether the angle and tightness of the door magnet are appropriate

  • ○

    Checking the AC actuator cable