You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?
Select an option, then click Submit answer.
-
○
Schedule change control
-
○
Scope change control
-
○
Integrated change control
-
○
Change Control Board approval process